    Chemical plant: 24" Phenol Pipeline Maintain
    date / 2017-09-22 14:35:54  read /
    This project finished in Sep.2016. It’s a rental project, owner required NODHA supply the 24” cold cutting machine and operator, owner supply the lifting equipment.

    On site cold cutting in chemical plant require explosion proof operation, so we bring ODP-610 go to the site, below pictures show how to lifting the equipment to working site, how to split the frame and job achieved.

    Lifting to Working Site
    Split the frame 
    Install the first half on the pipeline

    Owner: FORMOSA PHENOL(NINGBO) LIMITED COMPANY
    Project: 24” Phenol pipe line maintenance
    Site: Ningbo China
    Date: 17th Sep. 2016